A.G. Peltz placed 18,178 SY of 16” PCC and 6” Econocrete for a Brookley Field taxiway, completing phase 1 in Jan 2019 with precision paving...

Brookley Field Airport Apron

A.G. Peltz Group placed 18,178 SY of 16” PCC Pavement and 6” of Econocrete for a new taxiway project at Brookley Field in Mobile, AL. The project took 25 production days to complete with the first phase of the two-phase project completed in January of 2019. The PCC placement was completed with a Wirtgen 64 paver at 25’ lane widths with contraction joints sawn at 12.5’ intervals. The concrete was supplied by Bayou Concrete.

Work with us

With over 80 years of combined experience in our team and over 11,000,000 cubic yards of concrete placed across the US, A.G. Peltz Group are pioneers in the paving industry. More about us

We can handle your largest project from concept to creation.

Project Details

Owner

Mobile Airport Authority

Project Designer

Michael Baker International, Bobby Odom

General Contractor

John G Walton Construction

Completion Date

June 2019