Barbours Cut CY1N & 2N


AGP is in process of paving another 60,622 SY of 18″ RCC for Port Houston at Barbours Cut. As this project is being built in an operating terminal, coordination between the Port, paving contractor, and general contractor is paramount to ensure paving operations are completed in a timely and safe manner. Paving is being completed in stages with expectations for stage two to be completed in Spring 2020. Project suppliers include CEMEX, Vulcan Materials, and Alleyton Sand. AGP is utilizing various equipment including both ABG and Vogele Pavers, a Gomaco MTD, as well as a brand new Rapid Mix 600 Mixing plant.

Owner: Port Houston
General Contractor: McCarthy Building Companies
Engineer: HVJ Associates, Frank Carmichael